Worsley Alumina Project | Bridges in Asia | Federation Square | Olympic Edition | Galvanizing in Architecture | Hotel Restaurant | City Link | Transmission Towers | Aquatic Centre Essendon | Ampol Refinery | House by the Sea | Benetton’s Production Centre | Galvanized Sculptures | Geelong Carousel | Car Park | Galvanized Lintels | Health Care | Galvanized Reinforcement | School | Railway Tunnel | Sports & Aquatic Centre | Marine Service | Indoor Swimming Pool | Steel Reinforcement | Daintree Discovery Centre | Boardwalk
A Highway to the Future

Melbourne City Link Project - Western Link Section
PROJECT OVERVIEW
The Western Link section of the Melbourne City Link
Project will provide a long awaited connection between
two major arterial roads, the Tullamarine Freeway and
the West Gate Freeway.
The scope of work for the Western Link Project includes:
Upgrading and widening 7.5km of the existing Tullamarine
Freeway to eight lanes between Bulla Road and Flemington
Road. Additional features include the following:
- 7.5kms of widening of existing Freeway (2 lanes to 4
lanes)
- Approximately 265,000m3 bulk earthworks
- Upgrading or extending 15 bridges and overpasses
- Approximately 15km of noise attenuation walls to be constructed
- Extensive landscaping plans
Construction of a new 4.2km long elevated road joining
the Tullamarine Freeway to the West Gate Freeway and
3.5km of on and off ramps constructed in addition to
the main roadway. Additional features include the following:
- Match cast segmental span by span erection
- Approximately 210 Piers (5-20m high) constructed.
- Over 4,500 pre-cast concrete piles
- Approximately 3,500 segments to be produced
- Three lane segments weighing between 51-80t each
- Two lane segments weighing between 45-66t each
Construction of a new 490m balanced cantilever bridge
to carry the Freeway link across the Yarra River. Additional
features include the following:
- Construction of two 140m towers (6.5m2) for architectural
purposes on either side of the bridge
- 30m clearance at high tide
- Dual Carriageway
STEEL DESIGN AND PROTECTION
This work included a stringent corrosion protection
design life of up to 100 years with over 25 years to
first maintenance undertakings required.
Design considerations assessed the corrosivity of the
service environment, including the influence of prevailing
winds, microclimatic effects, industrial influences and
the severe effect of ultra violet exposure on materials
over long periods.
After thorough research, hot dip galvanizing was employed
on evidence of first cost saving and meeting long term
requirement
ELEVATED ROAD ENCLOSURE - NOISE ATTENUATION - TUBE STRUCTURE
An Architectural Bypass
This unique component of the Western Link completes
the freeway connection between the West Bound and Northern
Freeways.
Due to its proximity to the Debneys Park estate, an
innovative noise abatement structure has been designed
to 'house' the passing traffic, over a 300 metre section
of the elevated freeway.
Substantial enclosure of the roadway required a unique
elliptical steel design to accommodate the road lanes
passing through the architectonic tunnel.
The structure is also designed to accommodate an alignment
curve with a radius of 750 metres in the progress of
the road. Of the 1600 tonnes of steel involved in the
structure, the steel frames and outer plating sections
are hot dip galvanized while the internal frames are
painted.
In this instance hot dip galvanizing was also chosen
for aesthetic reasons, where architects recognised the
powerful set of forms and futuristic appearance of the
structure and preferred galvanizing for its natural silver
metallic finish to match the scale and effect of their
design.
The tube structure accommodates 6 x 3.5 metre wide traffic
lanes in a 45-50 metre overall width.
NOISE WALL BARRIERS
About 15 kilometres and 65,000 square metres of noise
attenuation wall have been constructed in reflective
cement panels with some sections containing further sound
trap embedment features.
The panels are supported by hot dip galvanized steel
columns of dimensions to accommodate the undulating terrain
and contours of the wall design.
SOIL REINFORCING
To meet the tight width constraints of the freeway space,
a system of soil nails of some 6 metres in length were
drilled and grouted as a means of accommodating retaining
walls. The 6 metre steel rods were also hot dip galvanized
to ensure the required steel service life in the buried
environment.
Client: Transurban City Link
Architects: Denton Corker Marshall
Consulting Engineers: Hyder CMP Joint Venture Main Contractor:
Transfield Obayashi Joint Venture
Sub Contractor: Baulderstone Hornibrook Engineering
Steel Fabricators: GFC Industries Pty Ltd - Elevated
|