|
Worsley Alumina Project | Bridges in Asia | Federation Square | Olympic Edition | Galvanizing in Architecture | Hotel Restaurant | City Link | Transmission Towers | Aquatic Centre Essendon | Ampol Refinery | House by the Sea | Benetton’s Production Centre | Galvanized Sculptures | Geelong Carousel | Car Park | Galvanized Lintels | Health Care | Galvanized Reinforcement | School | Railway Tunnel | Sports & Aquatic Centre | Marine Service | Indoor Swimming Pool | Steel Reinforcement | Daintree Discovery Centre | Boardwalk
Woresly Alumina Expansion Project


Outline of Objectives
The purpose of the Worsley Joint Venture extension was
to increase refinery capacity from 1.88mt/pa to 3.1mt/pa
at minimal cost, within the shortest project duration.
To achieve the objectives required innovative process
and plant design, creating an obvious opportunity to
introduce the latest technology.
During the feasibility study for the new plant, existing
construction practices were carefully scrutinized with
the object of finding maximum efficiencies to establish
economic justification.
Existing methods and materials were re-examined and
previous industry standards challenged to find the optimum
specification.
Planning and Construction
As reported by the Australian Steel Institute’s
Manager for Western Australia and South Australia, Rupert
Grayston,
“The construction manager for the project was
the Kaiser Bechtel Joint Venture (KBJV) with United Constructions,
the main steel fabricator, being part of the integrated
team. The project was completed without interrupting
the operation of the existing plant where work included
extension of currently operating units. Accurate and
timely supply was critical to meet the tight requirements
of the program, which included the delivery of 8000 tonnes
of structural steel work over a 12-month period. The
success of this planning was confirmed by achievement
of a series of key performance measures ranging from
high quality fieldwork through to time and material savings.
KBJV used 3D structural modelling software coordinating
with detailing and fabricator’s software to manage
stocks and for numeric controlled process machinery”.
According to Chief Structural Engineer, Paul Rushton,
“The 3D technology applied simultaneously to design
and detailing allowed the structures to be built in ‘virtual
reality’ in the design office, with concurrent
referencing of the models from the other disciplines.
In this way no surprises occurred later on-site, and
fit-up to existing structures was excellent.”
“The design process was completed by re-importing
the steel detail model back into the 3D process. In this
way, clashes with the components of other disciplines
such as chutes, equipment, piping etc were eliminated,” said
Rushton.
Steel Protection
In the context of the design upgrade, past practice had
been to avoid metallic coatings for steel protection.
This had been done on a precautionary basis and with
respect to the chemicals used in the alumina process.
However on examination of existing galvanized items
dispersed throughout the plant, such as cable trays and
other steel auxiliaries, excellent service life was proven,
prompting its consideration in the reassessment.
Particular value was found in galvanized steel handling
capability, solar radiation (UV) immunity, sharp edge
protection and other characteristics complementary to
the design capability of steel. Also of significance,
after-fabrication galvanized coating confers environmental
cleanliness, sustainability and a wholly Australian content
system. Collectively these contributed to construction
efficiency and to low life cycle cost and led to its
adoption for the project.
Summary
Rupert Grayston commented that "The Worsley experience
has shown that an intense focus on Total Installed Cost
is the meaningful project management parametric of the
new workflow.
In addition to the cost benefits, this new approach
offers:
- Schedule improvements
- Quality improvements
- Improved project control
- Contracting flexibility
- Reduced risk
The Worsley Expansion Project has represented a significant
step forward in new technology utilisation for the steel
construction industry. As software products and integration
techniques continue to advance, and as subsequent projects
further push the boundaries, the performances of Australian
projects and industry will continue to improve.”
Acknowledgements:
Paul Rushton, Chief Structural Engineer, Kaiser Bechtel
Joint Venture (KBJV)
Rupert Grayston, Western Australia and South Australia
State Manager, Australian Steel Institute
|